The central goal of construction stakeholders is to successfully deliver projects to stated
objective (s). However, for decades, construction projects have been plagued by perennial
constraints of cost and time overruns, poor quality, and lack of sustainability. The objective of
this paper is to identify and assess the constraints to construction project delivery, and to
recommend solutions to enhance project performance. This paper adopted both quantitative
and qualitative methods to establish the constraints in the Nigerian construction industry. A
pilot survey and literature reviewed revealed a total of fifty (50) construction constraints,
which were further classified into eight (8) major groups. Well-structured questionnaires were
administered to construction stakeholders (client, consultant and contractor) in Abuja, the
federal capital city of Nigeria. Relative Importance Index (RII) was used to analyze the data
using Likert scale. The results suggest that cost/time overrun related factors (inability to
reduce project cost), Stakeholders interactive-related factors (inability to establish client value
system), Client-related factors (Delay in interim payment and finance problem), and Labor/
material-related factors (escalation of material prices and materials quality variability) are the
most prevalent constraints in the Nigerian construction environment. To mitigate the effects
of these challenges, it is suggested that a formal innovative approach should be used by
stakeholders to address the problems of poor communication, high project cost, and delay.
Clients should also take measures to provide adequate funding and should promptly honor
interim certificates